Which type of contract is most appropriate when the scope of work is highly uncertain and detailed specifications cannot be clearly defined at the outset?
Time and materials contracts are suitable for uncertain scopes, as they allow payment for actual hours worked and materials used.
Start free practice for Supply Chain Management Professional (SCMP)
200 questions · no signup required · 40 free questions per day
Question: Which type of contract is most appropriate when the scope of work is highly uncertain and detailed specifications cannot be clearly defined at the outset?
Answer options:
- Fixed-price contract
- Cost-plus-fixed-fee contract ✅ Time and materials contract
- Incentive contract
Correct answer: Time and materials contract
Explanation: Time and materials contracts are suitable for uncertain scopes, as they allow payment for actual hours worked and materials used.
Start free practice for Supply Chain Management Professional (SCMP)
200 questions · no signup required · 40 free questions per day
More about Supply Chain Management Professional (SCMP)
More for Supply Chain Management Professional (SCMP) candidates
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Supply Chain Management Professional (SCMP) Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.