In project management for supply chain initiatives, the critical path method (CPM) identifies:
The critical path is the longest sequence of dependent activities in a project, determining the minimum time required for project completion.
Start free practice for Supply Chain Management Professional (SCMP)
200 questions · no signup required · 40 free questions per day
Question: In project management for supply chain initiatives, the critical path method (CPM) identifies:
Answer options:
- The most expensive activities. ✅ The longest sequence of tasks that must be completed on time for the project to finish on schedule.
- The task with the highest risk.
- The shortest possible project duration.
Correct answer: The longest sequence of tasks that must be completed on time for the project to finish on schedule.
Explanation: The critical path is the longest sequence of dependent activities in a project, determining the minimum time required for project completion.
Start free practice for Supply Chain Management Professional (SCMP)
200 questions · no signup required · 40 free questions per day
More about Supply Chain Management Professional (SCMP)
More for Supply Chain Management Professional (SCMP) candidates
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Supply Chain Management Professional (SCMP) Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.