Welder Red Seal · Question
A welding company certified to CSA W47.1 has recently started using a new type of shielding gas for their Gas Metal Arc Welding (GMAW) process. The previously qualified WPS only specified the old shielding gas. What action is required before this new shielding gas can be used on critical structural components?
Under CSA W47.1 (and similar codes like ASME Section IX), a change in shielding gas composition or type for GMAW is generally considered an essential variable f
Start free practice for Welder Red Seal
154 questions · no signup required · 40 free questions per day
Question: A welding company certified to CSA W47.1 has recently started using a new type of shielding gas for their Gas Metal Arc Welding (GMAW) process. The previously qualified WPS only specified the old shielding gas. What action is required before this new shielding gas can be used on critical structural components?
Answer options:
- No action is required, as shielding gas is a non-essential variable.
- The company must conduct a new welder qualification test with the new gas. ✅ A new Welding Procedure Specification (WPS) must be qualified with the new shielding gas.
- The welding engineer must simply approve the change without re-qualification.
Correct answer: A new Welding Procedure Specification (WPS) must be qualified with the new shielding gas.
Explanation: Under CSA W47.1 (and similar codes like ASME Section IX), a change in shielding gas composition or type for GMAW is generally considered an essential variable for the WPS. This means that if a new shielding gas is introduced, a new WPS must be created and qualified through testing to ensure that the change does not adversely affect the mechanical properties or integrity of the weld. It's not enough for an engineer to just approve it, and welder qualification is separate from WPS qualification.
Start free practice for Welder Red Seal
154 questions · no signup required · 40 free questions per day
More about Welder Red Seal
Related Questions
- A welder is fabricating a pressure vessel component using FCAW-G with an E70T-1 wire. The procedure specifies
- A welder is preparing to weld 20 mm (0.8 in) thick high-strength low-alloy (HSLA) steel using FCAW-G. The weld
- A structural steel fabricator is using FCAW-S (E71T-8 wire) to weld heavy sections of structural steel in an o
- When performing FCAW-G (gas-shielded flux-cored arc welding), a welder notices the arc is unstable and the wir
- A structural welder is performing overhead FCAW-G on 12 mm (0.5 in) thick steel with an E71T-1 wire. The weld
- A welder is setting up an FCAW-S machine for welding in a remote location without access to external shielding
More for Welder Red Seal candidates
Practice tests
Question explanations
- A welder is fabricating a pressure vessel component using FCAW-G with an E70T-1 wire. The procedure specifies
- A welder is preparing to weld 20 mm (0.8 in) thick high-strength low-alloy (HSLA) steel using FCAW-G. The weld
- A structural steel fabricator is using FCAW-S (E71T-8 wire) to weld heavy sections of structural steel in an o
- When performing FCAW-G (gas-shielded flux-cored arc welding), a welder notices the arc is unstable and the wir
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Welder Red Seal Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.