A carpenter is estimating materials for a 10 m x 12 m concrete slab that is 150 mm thick. If concrete is ordered in cubic meters, how many cubic meters of concrete are required, accounting for 5% waste?
First, calculate the volume of the slab: 10 m x 12 m x 0.150 m = 18.0 m³. Then, add 5% for waste: 18.0 m³ x 1.05 = 18.9 m³. Options A and C do not account for t
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpenter is estimating materials for a 10 m x 12 m concrete slab that is 150 mm thick. If concrete is ordered in cubic meters, how many cubic meters of concrete are required, accounting for 5% waste?
Answer options:
- 18.0 m³ ✅ 18.9 m³
- 20.0 m³
- 20.5 m³
Correct answer: 18.9 m³
Explanation: First, calculate the volume of the slab: 10 m x 12 m x 0.150 m = 18.0 m³. Then, add 5% for waste: 18.0 m³ x 1.05 = 18.9 m³. Options A and C do not account for the correct volume or waste.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.