A carpenter is estimating materials for a 10 m x 12 m concrete slab that is 150 mm thick. If concrete is ordered in cubic meters, how many cubic meters of concrete are required, accounting for 5% waste?

First, calculate the volume of the slab: 10 m x 12 m x 0.150 m = 18.0 m³. Then, add 5% for waste: 18.0 m³ x 1.05 = 18.9 m³. Options A and C do not account for t

Start free practice for Carpenter Red Seal Exam Prep

300 questions · no signup required · 40 free questions per day

Start Practice →

Question: A carpenter is estimating materials for a 10 m x 12 m concrete slab that is 150 mm thick. If concrete is ordered in cubic meters, how many cubic meters of concrete are required, accounting for 5% waste?

Answer options:

  • 18.0 m³ ✅ 18.9 m³
  • 20.0 m³
  • 20.5 m³

Correct answer: 18.9 m³

Explanation: First, calculate the volume of the slab: 10 m x 12 m x 0.150 m = 18.0 m³. Then, add 5% for waste: 18.0 m³ x 1.05 = 18.9 m³. Options A and C do not account for the correct volume or waste.

Start free practice for Carpenter Red Seal Exam Prep

300 questions · no signup required · 40 free questions per day

Start Practice →

More about Carpenter Red Seal Exam Prep

Related Questions

More for Carpenter Red Seal Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Carpenter Red Seal Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.