Carpenter Red Seal Exam Prep · Question
A small residential framing project requires 80 hours of labour per week for 4 weeks. If the hourly rate for a journeyperson carpenter, including benefits and overhead, is $65.00, what is the total estimated labour cost for this project?
The total labour hours are 80 hours/week * 4 weeks = 320 hours. The total labour cost is 320 hours * $65.00/hour = $20,800.00. The other options are incorrect c
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A small residential framing project requires 80 hours of labour per week for 4 weeks. If the hourly rate for a journeyperson carpenter, including benefits and overhead, is $65.00, what is the total estimated labour cost for this project?
Answer options:
- $20,800.00 ✅ $23,400.00
- $26,000.00
- $31,200.00
Correct answer: $23,400.00
Explanation: The total labour hours are 80 hours/week * 4 weeks = 320 hours. The total labour cost is 320 hours * $65.00/hour = $20,800.00. The other options are incorrect calculations of total hours or cost.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.