A small residential framing project requires 80 hours of labour per week for 4 weeks. If the hourly rate for a journeyperson carpenter, including benefits and overhead, is $65.00, what is the total estimated labour cost for this project?

The total labour hours are 80 hours/week * 4 weeks = 320 hours. The total labour cost is 320 hours * $65.00/hour = $20,800.00. The other options are incorrect c

Start free practice for Carpenter Red Seal Exam Prep

300 questions · no signup required · 40 free questions per day

Start Practice →

Question: A small residential framing project requires 80 hours of labour per week for 4 weeks. If the hourly rate for a journeyperson carpenter, including benefits and overhead, is $65.00, what is the total estimated labour cost for this project?

Answer options:

  • $20,800.00 ✅ $23,400.00
  • $26,000.00
  • $31,200.00

Correct answer: $23,400.00

Explanation: The total labour hours are 80 hours/week * 4 weeks = 320 hours. The total labour cost is 320 hours * $65.00/hour = $20,800.00. The other options are incorrect calculations of total hours or cost.

Start free practice for Carpenter Red Seal Exam Prep

300 questions · no signup required · 40 free questions per day

Start Practice →

More about Carpenter Red Seal Exam Prep

Related Questions

More for Carpenter Red Seal Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Carpenter Red Seal Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.