A construction project manager is reviewing the critical path of a residential subdivision development. The current schedule indicates that the 'underground utility installation' task is causing a delay. Which of the following activities is most likely a direct successor to this task and would also be impacted by its delay?
While road paving is related to utilities, the most direct successor affected by a delay in underground utility installation, especially for the houses themselv
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A construction project manager is reviewing the critical path of a residential subdivision development. The current schedule indicates that the 'underground utility installation' task is causing a delay. Which of the following activities is most likely a direct successor to this task and would also be impacted by its delay?
Answer options:
- Road paving
- Rough framing of houses
- Final landscaping ✅ Foundation excavation for houses
Correct answer: Foundation excavation for houses
Explanation: While road paving is related to utilities, the most direct successor affected by a delay in underground utility installation, especially for the houses themselves, would be the foundation excavation, as utilities often need to be in place or at a certain stage before foundations can be dug or poured. Rough framing typically follows foundation work, and final landscaping is near the end of the project.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.