During the planning phase of a multi-storey wood-frame building, the project scheduler identifies that craning activities for floor joists and roof trusses are on the critical path. The crane is also scheduled for another project concurrently. What is the most effective strategy to mitigate the risk of schedule delays due to crane availability?
To mitigate schedule delays due to crane availability on the critical path, identifying alternative hoisting methods or securing exclusive crane use during crit
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: During the planning phase of a multi-storey wood-frame building, the project scheduler identifies that craning activities for floor joists and roof trusses are on the critical path. The crane is also scheduled for another project concurrently. What is the most effective strategy to mitigate the risk of schedule delays due to crane availability?
Answer options:
- Increase the budget for material waste.
- Pad the schedule by adding 20% extra time to all subsequent tasks. ✅ Identify alternative hoisting methods or negotiate exclusive crane use for specific, critical windows of time.
- Reduce the quality control inspections to save time.
Correct answer: Identify alternative hoisting methods or negotiate exclusive crane use for specific, critical windows of time.
Explanation: To mitigate schedule delays due to crane availability on the critical path, identifying alternative hoisting methods or securing exclusive crane use during critical periods directly addresses the bottleneck. Padding the schedule or increasing material waste budget does not resolve the core issue, and reducing quality control is not a viable or safe option.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.