Carpenter Red Seal Exam Prep · Question
A carpenter is estimating the cost of installing 50 square metres of hardwood flooring. The material cost is $45.00 per square metre. The labour rate is $60.00 per hour, and it takes approximately 0.25 hours per square metre to install. What is the total estimated cost for material and labour?
Material cost = 50 m² x $45.00/m² = $2,250.00. Labour hours = 50 m² x 0.25 hr/m² = 12.5 hours. Labour cost = 12.5 hours x $60.00/hour = $750.00. Total estimated
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpenter is estimating the cost of installing 50 square metres of hardwood flooring. The material cost is $45.00 per square metre. The labour rate is $60.00 per hour, and it takes approximately 0.25 hours per square metre to install. What is the total estimated cost for material and labour?
Answer options: ✅ $2,250.00
- $750.00
- $3,000.00
- $3,750.00
Correct answer: $2,250.00
Explanation: Material cost = 50 m² x $45.00/m² = $2,250.00. Labour hours = 50 m² x 0.25 hr/m² = 12.5 hours. Labour cost = 12.5 hours x $60.00/hour = $750.00. Total estimated cost = $2,250.00 + $750.00 = $3,000.00.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.