A superintendent is using a Gantt chart to manage a large commercial fit-out. The flooring installation task has been delayed by 3 working days due to unforeseen subfloor repairs. The painting task is scheduled to start immediately after flooring is complete. If painting was originally scheduled to take 5 working days, and the overall project completion date cannot be shifted, what is the most likely impact on the project schedule?
If flooring is delayed and painting is directly dependent on it without any float, then the overall project completion date will be delayed by the same amount a
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A superintendent is using a Gantt chart to manage a large commercial fit-out. The flooring installation task has been delayed by 3 working days due to unforeseen subfloor repairs. The painting task is scheduled to start immediately after flooring is complete. If painting was originally scheduled to take 5 working days, and the overall project completion date cannot be shifted, what is the most likely impact on the project schedule?
Answer options:
- The painting task will take longer, increasing its duration to 8 working days.
- The painting task will need to be re-scheduled to finish 3 days earlier than planned, assuming no float.
- Other tasks on non-critical paths will need to be accelerated to compensate. ✅ The overall project completion date will be delayed by 3 working days unless there is float in the critical path somewhere after flooring.
Correct answer: The overall project completion date will be delayed by 3 working days unless there is float in the critical path somewhere after flooring.
Explanation: If flooring is delayed and painting is directly dependent on it without any float, then the overall project completion date will be delayed by the same amount as the flooring delay (3 working days), unless there is enough float in subsequent tasks on the critical path to absorb this delay. The painting task itself will still take 5 days, it just starts later. Accelerating non-critical path tasks would not help if painting is on the critical path.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.