A framing crew is installing I-joists for a large open-concept living area. The architectural drawings specify a large opening for a stairwell through the floor system. Which of the following is the most appropriate method to frame this opening while maintaining structural integrity?
For openings in an I-joist floor system, a header must be installed between two carrying joists to support the cut ends of the I-joists. This creates a strong b
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A framing crew is installing I-joists for a large open-concept living area. The architectural drawings specify a large opening for a stairwell through the floor system. Which of the following is the most appropriate method to frame this opening while maintaining structural integrity?
Answer options:
- Cut the I-joists that run through the opening flush with the opening edge and rely on the subfloor for support. ✅ Install headers (trimmers) between two full-length parallel I-joists (carrying joists) to support the cut ends of the I-joists.
- Use steel angle brackets to attach the cut I-joists directly to the adjacent uncut I-joists.
- Reinforce the cut I-joists with plywood gussets glued and screwed over the webs.
Correct answer: Install headers (trimmers) between two full-length parallel I-joists (carrying joists) to support the cut ends of the I-joists.
Explanation: For openings in an I-joist floor system, a header must be installed between two carrying joists to support the cut ends of the I-joists. This creates a strong box-out. Cutting joists flush without support, using only angle brackets, or simply gusseting cut webs would compromise the structural integrity for a stairwell opening.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.