A carpenter is working on a roof with a 6:12 pitch. The work requires kneeling and moving across the roof surface to install shingles. What type of fall protection is most appropriate and effective for this specific task, assuming no guardrails are installed?
On a roof with a 6:12 pitch (26.5 degrees), fall arrest systems are generally required whenever there is a risk of falling 3 metres or more. A full-body harness
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpenter is working on a roof with a 6:12 pitch. The work requires kneeling and moving across the roof surface to install shingles. What type of fall protection is most appropriate and effective for this specific task, assuming no guardrails are installed?
Answer options:
- A safety net positioned below the work area. ✅ A full-body harness with a fall arrest lanyard anchored to a peak anchor point.
- Warning lines and safety monitors.
- Personal flotation device (PFD) and safety helmet.
Correct answer: A full-body harness with a fall arrest lanyard anchored to a peak anchor point.
Explanation: On a roof with a 6:12 pitch (26.5 degrees), fall arrest systems are generally required whenever there is a risk of falling 3 metres or more. A full-body harness with a fall arrest lanyard anchored to a suitable peak anchor point provides the most effective personal fall protection for a worker actively moving and working on such a sloped surface. Warning lines are typically for flat roofs, and safety nets are a collective protection measure, often used when individual fall arrest is impractical.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.