Carpenter Red Seal Exam Prep · Question
A carpenter is constructing interior partition walls. The project manager indicates that the framing must be completed before the electrical rough-in can begin, and the electrical rough-in must be finished before insulation and drywall. This sequence is an example of what type of dependency?
This describes a mandatory dependency, which is inherent in the nature of the work where one task cannot start until another is completed (e.g., framing before
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpenter is constructing interior partition walls. The project manager indicates that the framing must be completed before the electrical rough-in can begin, and the electrical rough-in must be finished before insulation and drywall. This sequence is an example of what type of dependency?
Answer options:
- Critical Path dependency
- Discretionary dependency ✅ Mandatory dependency
- External dependency
Correct answer: Mandatory dependency
Explanation: This describes a mandatory dependency, which is inherent in the nature of the work where one task cannot start until another is completed (e.g., framing before electrical rough-in). Discretionary dependencies are defined by the project team, critical path is a sequencing method, and external dependencies involve outside stakeholders.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.