A carpenter is constructing interior partition walls. The project manager indicates that the framing must be completed before the electrical rough-in can begin, and the electrical rough-in must be finished before insulation and drywall. This sequence is an example of what type of dependency?

This describes a mandatory dependency, which is inherent in the nature of the work where one task cannot start until another is completed (e.g., framing before

Start free practice for Carpenter Red Seal Exam Prep

300 questions · no signup required · 40 free questions per day

Start Practice →

Question: A carpenter is constructing interior partition walls. The project manager indicates that the framing must be completed before the electrical rough-in can begin, and the electrical rough-in must be finished before insulation and drywall. This sequence is an example of what type of dependency?

Answer options:

  • Critical Path dependency
  • Discretionary dependency ✅ Mandatory dependency
  • External dependency

Correct answer: Mandatory dependency

Explanation: This describes a mandatory dependency, which is inherent in the nature of the work where one task cannot start until another is completed (e.g., framing before electrical rough-in). Discretionary dependencies are defined by the project team, critical path is a sequencing method, and external dependencies involve outside stakeholders.

Start free practice for Carpenter Red Seal Exam Prep

300 questions · no signup required · 40 free questions per day

Start Practice →

More about Carpenter Red Seal Exam Prep

Related Questions

More for Carpenter Red Seal Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Carpenter Red Seal Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.