A project schedule indicates that the 'roof sheeting' activity has a float of 5 days, and the 'truss installation' activity must be completed before 'roof sheeting' can start. If 'truss installation' is delayed by 3 days, what impact does this have on the project's critical path?
Float is the amount of time an activity can be delayed without delaying the project's critical path or subsequent activities. Since the delay (3 days) is less t
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A project schedule indicates that the 'roof sheeting' activity has a float of 5 days, and the 'truss installation' activity must be completed before 'roof sheeting' can start. If 'truss installation' is delayed by 3 days, what impact does this have on the project's critical path?
Answer options:
- The critical path is delayed by 3 days. ✅ The critical path is not affected.
- The critical path is delayed by 5 days.
- The critical path is accelerated by 2 days.
Correct answer: The critical path is not affected.
Explanation: Float is the amount of time an activity can be delayed without delaying the project's critical path or subsequent activities. Since the delay (3 days) is less than the available float (5 days) for the 'roof sheeting' activity, the critical path will not be affected. The float for 'roof sheeting' will be reduced to 2 days.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.