A carpentry foreman is reviewing a project schedule and observes a task, 'Install interior doors,' with a 'finish-to-start' dependency on 'Drywall Installation Complete.' The drywall is estimated to take 10 days to complete. If the project team decides to overlap these activities by starting to hang doors on the 8th day of drywall installation in different sections of the building, what scheduling technique is being applied?
Fast-tracking is a scheduling technique where activities that would normally be done in sequence are performed in parallel or overlapped. By starting door insta
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpentry foreman is reviewing a project schedule and observes a task, 'Install interior doors,' with a 'finish-to-start' dependency on 'Drywall Installation Complete.' The drywall is estimated to take 10 days to complete. If the project team decides to overlap these activities by starting to hang doors on the 8th day of drywall installation in different sections of the building, what scheduling technique is being applied?
Answer options:
- Crashing ✅ Fast-tracking
- Resource levelling
- Critical Chain Method
Correct answer: Fast-tracking
Explanation: Fast-tracking is a scheduling technique where activities that would normally be done in sequence are performed in parallel or overlapped. By starting door installation before drywall is fully complete, the team is overlapping activities to shorten the overall project duration. Crashing involves adding resources, resource levelling smooths resource usage, and critical chain method focuses on managing bottlenecks.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.