A carpenter is preparing to pour a residential concrete footing. The local building code specifies a minimum footing depth of 450 mm below undisturbed grade in this region. The existing grade is 200 mm above the proposed top of footing. What is the minimum excavation depth required from the existing grade?
To determine the minimum excavation depth from existing grade, you add the required footing depth below undisturbed grade (450 mm) to the distance the existing
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpenter is preparing to pour a residential concrete footing. The local building code specifies a minimum footing depth of 450 mm below undisturbed grade in this region. The existing grade is 200 mm above the proposed top of footing. What is the minimum excavation depth required from the existing grade?
Answer options:
- 250 mm
- 450 mm ✅ 650 mm
- 700 mm
Correct answer: 650 mm
Explanation: To determine the minimum excavation depth from existing grade, you add the required footing depth below undisturbed grade (450 mm) to the distance the existing grade is above the proposed top of footing (200 mm). This totals 650 mm. If only 250 mm was excavated, the footing would not meet the required depth below grade.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.