A carpenter is checking the rebar lap splices in a foundation wall beam. The design drawings specify a Class B lap splice length for 25M bars. What is the primary function of a lap splice in rebar?
The primary function of a lap splice is to provide continuity in rebar by transferring tensile or compressive forces from one bar to another, ensuring the struc
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpenter is checking the rebar lap splices in a foundation wall beam. The design drawings specify a Class B lap splice length for 25M bars. What is the primary function of a lap splice in rebar?
Answer options:
- To provide a decorative finish to the rebar
- To allow for future expansion and contraction of the concrete ✅ To transfer tensile or compressive stress from one rebar to an adjacent rebar
- To anchor electrical conduits within the concrete
Correct answer: To transfer tensile or compressive stress from one rebar to an adjacent rebar
Explanation: The primary function of a lap splice is to provide continuity in rebar by transferring tensile or compressive forces from one bar to another, ensuring the structural integrity of the reinforced concrete member. They do not serve decorative purposes, facilitate expansion, or anchor conduits.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.