Carpenter Red Seal Exam Prep · Question
A concrete footing is being prepared, and the rebar schedule calls for 15M reinforcing bars to be placed with a minimum concrete cover of 75 mm from the bottom and sides. What is the most effective way to ensure the bottom reinforcing steel maintains the specified cover during concrete placement?
Pre-cast concrete blocks, also known as chairs or dobies, are specifically designed to support reinforcing steel at the correct height, ensuring the specified c
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A concrete footing is being prepared, and the rebar schedule calls for 15M reinforcing bars to be placed with a minimum concrete cover of 75 mm from the bottom and sides. What is the most effective way to ensure the bottom reinforcing steel maintains the specified cover during concrete placement?
Answer options:
- Suspending the rebar using wires attached to the formwork.
- Placing the rebar directly on the excavated soil. ✅ Using pre-cast concrete blocks (dobies or chairs) of the appropriate height.
- Relying on the concrete slump to lift the rebar into position.
Correct answer: Using pre-cast concrete blocks (dobies or chairs) of the appropriate height.
Explanation: Pre-cast concrete blocks, also known as chairs or dobies, are specifically designed to support reinforcing steel at the correct height, ensuring the specified concrete cover is maintained from the bottom of the footing. Suspending with wires is less reliable and difficult to adjust, placing directly on soil eliminates cover, and concrete slump cannot reliably lift and hold rebar in place.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.