Carpenter Red Seal Exam Prep · Question
A carpenter is leading a team on a tight deadline to complete the flooring installation for a multi-floor office building. Due to material delivery delays, the project is five days behind schedule. To mitigate this, the carpenter proposes 'crashing' the schedule. Which of the following best describes this technique in this context?
Crashing a schedule involves adding resources (e.g., more workers, equipment) or working overtime to shorten the duration of critical path activities, thereby r
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpenter is leading a team on a tight deadline to complete the flooring installation for a multi-floor office building. Due to material delivery delays, the project is five days behind schedule. To mitigate this, the carpenter proposes 'crashing' the schedule. Which of the following best describes this technique in this context?
Answer options:
- Reordering tasks to start non-critical activities earlier.
- Reducing the scope of work to meet the deadline. ✅ Adding resources or working overtime to shorten critical path activities.
- Shifting the project completion date to accommodate the delay.
Correct answer: Adding resources or working overtime to shorten critical path activities.
Explanation: Crashing a schedule involves adding resources (e.g., more workers, equipment) or working overtime to shorten the duration of critical path activities, thereby reducing the overall project completion time. It does not involve reducing scope or simply shifting the deadline.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.