Carpenter Red Seal Exam Prep · Question
A framing crew is scheduled to begin erecting walls on a residential project. Before they can start, the foundation must be poured and cured, and the subfloor installed. Which scheduling technique is being primarily used to determine the start time for framing?
The Precedence Diagramming Method (PDM) explicitly focuses on the relationships between activities, including 'finish-to-start' dependencies, which is evident h
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A framing crew is scheduled to begin erecting walls on a residential project. Before they can start, the foundation must be poured and cured, and the subfloor installed. Which scheduling technique is being primarily used to determine the start time for framing?
Answer options:
- Critical Path Method (CPM).
- Just-in-Time (JIT) scheduling.
- Activity-on-Node (AON) diagramming. ✅ Precedence Diagramming Method (PDM).
Correct answer: Precedence Diagramming Method (PDM).
Explanation: The Precedence Diagramming Method (PDM) explicitly focuses on the relationships between activities, including 'finish-to-start' dependencies, which is evident here as framing cannot start until the previous activities are complete. CPM is a method to find the longest path, while JIT is about inventory, and AON is a type of diagram used in PDM.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.