A contractor is preparing a cost estimate for a detached garage project. After calculating all direct costs (labour, materials, equipment), what is typically added next to arrive at a total project cost for the client?

After direct costs, overhead (indirect costs) and profit margin are typically added to arrive at the total cost presented to the client, ensuring the business c

Start free practice for Carpenter Red Seal Exam Prep

300 questions · no signup required · 40 free questions per day

Start Practice →

Question: A contractor is preparing a cost estimate for a detached garage project. After calculating all direct costs (labour, materials, equipment), what is typically added next to arrive at a total project cost for the client?

Answer options: ✅ Profit margin and overhead costs.

  • Contingency for unforeseen issues.
  • Subcontractor bids for specialized trades.
  • An allowance for client-requested changes.

Correct answer: Profit margin and overhead costs.

Explanation: After direct costs, overhead (indirect costs) and profit margin are typically added to arrive at the total cost presented to the client, ensuring the business covers its operating expenses and earns revenue. Contingency is often included as part of direct or indirect costs, and subcontractor bids are direct costs, not subsequent additions.

Start free practice for Carpenter Red Seal Exam Prep

300 questions · no signup required · 40 free questions per day

Start Practice →

More about Carpenter Red Seal Exam Prep

Related Questions

More for Carpenter Red Seal Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Carpenter Red Seal Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.