A contractor is preparing a cost estimate for a detached garage project. After calculating all direct costs (labour, materials, equipment), what is typically added next to arrive at a total project cost for the client?
After direct costs, overhead (indirect costs) and profit margin are typically added to arrive at the total cost presented to the client, ensuring the business c
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A contractor is preparing a cost estimate for a detached garage project. After calculating all direct costs (labour, materials, equipment), what is typically added next to arrive at a total project cost for the client?
Answer options: ✅ Profit margin and overhead costs.
- Contingency for unforeseen issues.
- Subcontractor bids for specialized trades.
- An allowance for client-requested changes.
Correct answer: Profit margin and overhead costs.
Explanation: After direct costs, overhead (indirect costs) and profit margin are typically added to arrive at the total cost presented to the client, ensuring the business covers its operating expenses and earns revenue. Contingency is often included as part of direct or indirect costs, and subcontractor bids are direct costs, not subsequent additions.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.