Carpenter Red Seal Exam Prep · Question
A construction project manager is using a Gantt chart to track progress. Two critical path activities, 'foundation pour' (Activity A) and 'wall framing' (Activity B), have a finish-to-start relationship. Activity A is scheduled for 5 days, and Activity B for 8 days. Due to unexpected weather, Activity A is delayed by 2 days. What is the immediate impact on Activity B's earliest start date?
Since Activity A and B have a finish-to-start relationship and Activity A is on the critical path, a 2-day delay in Activity A directly pushes back Activity B's
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A construction project manager is using a Gantt chart to track progress. Two critical path activities, 'foundation pour' (Activity A) and 'wall framing' (Activity B), have a finish-to-start relationship. Activity A is scheduled for 5 days, and Activity B for 8 days. Due to unexpected weather, Activity A is delayed by 2 days. What is the immediate impact on Activity B's earliest start date?
Answer options: ✅ Activity B's earliest start date is delayed by 2 days.
- Activity B's duration is reduced by 2 days to compensate.
- Activity B can start simultaneously with Activity A to catch up.
- The project's overall completion date remains unaffected.
Correct answer: Activity B's earliest start date is delayed by 2 days.
Explanation: Since Activity A and B have a finish-to-start relationship and Activity A is on the critical path, a 2-day delay in Activity A directly pushes back Activity B's earliest possible start date by 2 days. Activity B cannot start until A is complete, and critical path activities have no float to absorb delays.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.