Carpenter Red Seal Exam Prep · Question
During concrete placement for deep walls, what is an acceptable method to minimize segregation and reduce pressure on formwork?
Using a tremie pipe or elephant trunk allows concrete to be placed directly at the bottom of deep forms, minimizing the drop height. This reduces segregation of
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: During concrete placement for deep walls, what is an acceptable method to minimize segregation and reduce pressure on formwork?
Answer options:
- Pouring the concrete rapidly from a high elevation. ✅ Using a concrete pump with a tremie pipe or elephant trunk.
- Adding excessive water to the concrete mix for increased flowability.
- Placing large rocks at the bottom of the forms as a filler.
Correct answer: Using a concrete pump with a tremie pipe or elephant trunk.
Explanation: Using a tremie pipe or elephant trunk allows concrete to be placed directly at the bottom of deep forms, minimizing the drop height. This reduces segregation of aggregates and lessens the impact pressure on the formwork.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.