During concrete placement for deep walls, what is an acceptable method to minimize segregation and reduce pressure on formwork?

Using a tremie pipe or elephant trunk allows concrete to be placed directly at the bottom of deep forms, minimizing the drop height. This reduces segregation of

Start free practice for Carpenter Red Seal Exam Prep

300 questions · no signup required · 40 free questions per day

Start Practice →

Question: During concrete placement for deep walls, what is an acceptable method to minimize segregation and reduce pressure on formwork?

Answer options:

  • Pouring the concrete rapidly from a high elevation. ✅ Using a concrete pump with a tremie pipe or elephant trunk.
  • Adding excessive water to the concrete mix for increased flowability.
  • Placing large rocks at the bottom of the forms as a filler.

Correct answer: Using a concrete pump with a tremie pipe or elephant trunk.

Explanation: Using a tremie pipe or elephant trunk allows concrete to be placed directly at the bottom of deep forms, minimizing the drop height. This reduces segregation of aggregates and lessens the impact pressure on the formwork.

Start free practice for Carpenter Red Seal Exam Prep

300 questions · no signup required · 40 free questions per day

Start Practice →

More about Carpenter Red Seal Exam Prep

Related Questions

More for Carpenter Red Seal Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Carpenter Red Seal Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.