Which of the following is the primary purpose of a 'blocking' or 'bridging' within a floor joist system?

Blocking or bridging, installed between floor joists, acts to prevent the joists from twisting or rotating, and helps to distribute concentrated loads spread ac

Start free practice for Carpenter Red Seal Exam Prep

300 questions · no signup required · 40 free questions per day

Start Practice →

Question: Which of the following is the primary purpose of a 'blocking' or 'bridging' within a floor joist system?

Answer options: ✅ To prevent joist rotation and distribute loads

  • To provide a nailing surface for subfloor sheathing
  • To create a chase for plumbing and electrical services
  • To enhance the seismic resistance of the structure

Correct answer: To prevent joist rotation and distribute loads

Explanation: Blocking or bridging, installed between floor joists, acts to prevent the joists from twisting or rotating, and helps to distribute concentrated loads spread across multiple joists.

Start free practice for Carpenter Red Seal Exam Prep

300 questions · no signup required · 40 free questions per day

Start Practice →

More about Carpenter Red Seal Exam Prep

Related Questions

More for Carpenter Red Seal Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Carpenter Red Seal Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.