Carpenter Red Seal Exam Prep · Question
When constructing a load-bearing wall with a window opening, what structural member transfers the vertical load from the wall above the opening to the jack studs?
The header (or lintel) is a horizontal beam installed above a window or door opening in a load-bearing wall. Its purpose is to transfer the structural load from
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: When constructing a load-bearing wall with a window opening, what structural member transfers the vertical load from the wall above the opening to the jack studs?
Answer options:
- The cripple stud
- The sill plate ✅ The header (lintel)
- The blocking
Correct answer: The header (lintel)
Explanation: The header (or lintel) is a horizontal beam installed above a window or door opening in a load-bearing wall. Its purpose is to transfer the structural load from the wall segment above the opening to the studs on either side.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.