A floor system requires a large opening for a fireplace hearth. Which type of beam is most likely specified to support the ends of the cut joists due to the concentrated load and span?
For large openings and concentrated loads, a steel wide-flange beam offers superior strength and stiffness compared to most wood alternatives, making it a commo
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A floor system requires a large opening for a fireplace hearth. Which type of beam is most likely specified to support the ends of the cut joists due to the concentrated load and span?
Answer options:
- A single dimensional lumber beam
- A built-up structural timber beam ✅ A steel wide-flange beam (W-beam)
- A small laminated veneer lumber (LVL) beam
Correct answer: A steel wide-flange beam (W-beam)
Explanation: For large openings and concentrated loads, a steel wide-flange beam offers superior strength and stiffness compared to most wood alternatives, making it a common choice where significant structural support is needed.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.