A carpenter is setting up for a new commercial building on a sloped site. The blueprint indicates a finished floor elevation (FFE) of 135.250 m at gridline A-1. The surveyor's benchmark (TBM) is established at 136.500 m. If the top of the foundation wall is to be 0.150 m below FFE, what is the required cut/fill measurement at the TBM to establish the top of the foundation wall elevation?
Finished foundation wall elevation = FFE - 0.150 m = 135.250 m - 0.150 m = 135.100 m. The difference from TBM = TBM - Foundation Wall Elev = 136.500 m - 135.100
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpenter is setting up for a new commercial building on a sloped site. The blueprint indicates a finished floor elevation (FFE) of 135.250 m at gridline A-1. The surveyor's benchmark (TBM) is established at 136.500 m. If the top of the foundation wall is to be 0.150 m below FFE, what is the required cut/fill measurement at the TBM to establish the top of the foundation wall elevation?
Answer options:
- 1.400 m fill
- 1.100 m cut ✅ 1.400 m cut
- 1.100 m fill
Correct answer: 1.400 m cut
Explanation: Finished foundation wall elevation = FFE - 0.150 m = 135.250 m - 0.150 m = 135.100 m. The difference from TBM = TBM - Foundation Wall Elev = 136.500 m - 135.100 m = 1.400 m. Since TBM is higher, it requires a cut.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.