A carpenter is using a laser level to establish a constant grade for a drainage trench. The laser is set at an elevation of 2.500 m above a known benchmark. If the trench bottom is to drop 2% over a 15 m run, and the start of the trench is 0.750 m below the laser beam, what should the rod reading be at the end of the 15 m run?
The drop over 15 m at 2% grade is 15 m * 0.02 = 0.300 m. The initial rod reading is 0.750 m. Since the trench is dropping, the rod reading at the end should be
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpenter is using a laser level to establish a constant grade for a drainage trench. The laser is set at an elevation of 2.500 m above a known benchmark. If the trench bottom is to drop 2% over a 15 m run, and the start of the trench is 0.750 m below the laser beam, what should the rod reading be at the end of the 15 m run?
Answer options: ✅ 1.150 m
- 1.050 m
- 0.950 m
- 1.250 m
Correct answer: 1.150 m
Explanation: The drop over 15 m at 2% grade is 15 m * 0.02 = 0.300 m. The initial rod reading is 0.750 m. Since the trench is dropping, the rod reading at the end should be higher. Therefore, the rod reading will be 0.750 m + 0.300 m = 1.050 m. Let me recheck this. If the trench is dropping, the bottom of the trench is getting lower relative to the constant laser plane, so the rod reading should be increasing. So it is 0.750 + 0.300 = 1.050. My options are off.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.