A concrete suspended slab formwork system is designed for a target concrete pour rate of 1.5 m/h. The concrete mix has a density of 2400 kg/m³ and vibrated concrete is assumed. To determine the maximum lateral pressure on the formwork, which formula is most appropriate under CSA S269.3 guidelines?
CSA S269.3, Clause 6.4.1 details formulas for lateral pressure. For concrete placed at a rate up to 3 m/h with vibration, the formula P_max = 6.44R / (T + 17.8)
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A concrete suspended slab formwork system is designed for a target concrete pour rate of 1.5 m/h. The concrete mix has a density of 2400 kg/m³ and vibrated concrete is assumed. To determine the maximum lateral pressure on the formwork, which formula is most appropriate under CSA S269.3 guidelines?
Answer options:
- P_max = ɣh ✅ P_max = 6.44R / (T + 17.8) + ɣh
- P_max = 7.2R / (T + 17.8)
- P_max = 1000 + 7.85R / (T + 17.8)
Correct answer: P_max = 6.44R / (T + 17.8) + ɣh
Explanation: CSA S269.3, Clause 6.4.1 details formulas for lateral pressure. For concrete placed at a rate up to 3 m/h with vibration, the formula P_max = 6.44R / (T + 17.8) + ɣh is used, provided other specific conditions for temperature and concrete density are met, and P_max is less than or equal to ɣH. This considers hydrostatic head (ɣh) and kinetic pressure components.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.