NBC 2020, Sentence 4.1.5.8.(1) specifies that the minimum specified live load for falsework to support concrete construction activities is 4.8 kPa. This account
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: According to the National Building Code of Canada (NBC) 2020, what is the minimum required design live load for horizontal falsework supporting concrete during construction, excluding impact and other specific loads?
Answer options:
- 2.4 kPa
- 3.6 kPa ✅ 4.8 kPa
- 5.0 kPa
Correct answer: 4.8 kPa
Explanation: NBC 2020, Sentence 4.1.5.8.(1) specifies that the minimum specified live load for falsework to support concrete construction activities is 4.8 kPa. This accounts for workers, equipment, and material associated with the pour.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.