Carpenter Red Seal Exam Prep · Question
What is the primary purpose of horizontal bracing in falsework for concrete slabs?
Horizontal bracing, often in the form of ledger boards or cross-bracing, is essential to connect vertical shores and prevent their lateral movement or buckling
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: What is the primary purpose of horizontal bracing in falsework for concrete slabs?
Answer options:
- To strengthen individual shores against bending.
- To transfer load from the slab to the ground. ✅ To prevent lateral displacement or buckling of vertical shores.
- To increase the speed of falsework erection.
Correct answer: To prevent lateral displacement or buckling of vertical shores.
Explanation: Horizontal bracing, often in the form of ledger boards or cross-bracing, is essential to connect vertical shores and prevent their lateral movement or buckling under axial load, which can lead to falsework instability and collapse as per CSA S269.3.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.