A concrete slab was poured with a Type 30 (HE) cement at an average temperature of 20°C. Compared to a slab poured with Type 10 (GU) cement under identical conditions, how would the curing time to reach a specified early strength likely differ?
Type 30 (HE) cement (High Early Strength) is formulated to achieve strength more rapidly than Type 10 (GU) (General Use) cement. Therefore, concrete made with T
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A concrete slab was poured with a Type 30 (HE) cement at an average temperature of 20°C. Compared to a slab poured with Type 10 (GU) cement under identical conditions, how would the curing time to reach a specified early strength likely differ?
Answer options:
- Type 30 (HE) concrete would require a longer curing time. ✅ Type 30 (HE) concrete would require substantially less curing time.
- The curing time would be identical for both types of cement.
- Type 30 (HE) is not typically used for slabs, so comparison is not relevant.
Correct answer: Type 30 (HE) concrete would require substantially less curing time.
Explanation: Type 30 (HE) cement (High Early Strength) is formulated to achieve strength more rapidly than Type 10 (GU) (General Use) cement. Therefore, concrete made with Type 30 (HE) cement would typically require substantially less curing time to reach a specified early strength, such as for formwork stripping, under similar temperature conditions.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.