Carpenter Red Seal Exam Prep · Question
A site plan indicates an existing sewer line running diagonally across the property. What type of line and what colour would typically be used to represent this on a site services drawing, according to common Canadian practice?
Service drawings commonly use a dashed brown line to indicate existing sanitary sewer lines. Different colours and line types are used to distinguish various ut
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A site plan indicates an existing sewer line running diagonally across the property. What type of line and what colour would typically be used to represent this on a site services drawing, according to common Canadian practice?
Answer options:
- A dashed green line
- A solid red line ✅ A dashed brown line
- A solid blue line
Correct answer: A dashed brown line
Explanation: Service drawings commonly use a dashed brown line to indicate existing sanitary sewer lines. Different colours and line types are used to distinguish various utilities and conditions on drawings.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.