Carpenter Red Seal Exam Prep · Question
A surveyor using a total station on a job site wants to confirm the property boundaries. If they shoot two known corner pins and the measured distance is 45.672 m, but the legal plan states 45.652 m, what is the discrepancy?
The discrepancy is the measured distance minus the planned distance: 45.672 m - 45.652 m = 0.020 m, which is 20 mm. The measurement is longer than the plan spec
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A surveyor using a total station on a job site wants to confirm the property boundaries. If they shoot two known corner pins and the measured distance is 45.672 m, but the legal plan states 45.652 m, what is the discrepancy?
Answer options: ✅ 20 mm longer than planned
- 20 mm shorter than planned
- 2 mm longer than planned
- 2 mm shorter than planned
Correct answer: 20 mm longer than planned
Explanation: The discrepancy is the measured distance minus the planned distance: 45.672 m - 45.652 m = 0.020 m, which is 20 mm. The measurement is longer than the plan specifies.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.