What is the primary function of vertical shores in a suspended concrete slab formwork system?
Vertical shores (props or posts) are crucial elements of falsework whose primary function is to directly support the vertical weight of the wet (and eventually
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: What is the primary function of vertical shores in a suspended concrete slab formwork system?
Answer options:
- To resist lateral concrete pressure
- To provide a walking surface for workers ✅ To support the dead load of wet concrete and live loads
- To transfer uplift forces to the foundation
Correct answer: To support the dead load of wet concrete and live loads
Explanation: Vertical shores (props or posts) are crucial elements of falsework whose primary function is to directly support the vertical weight of the wet (and eventually cured) concrete slab, including any additional construction live loads, transferring these loads safely to the supporting structure below.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.