A concrete slab was poured with Type 10 (normal) Portland cement. The average ambient temperature has been 10 °C. The specified minimum compressive strength for stripping is 15 MPa. If the concrete is expected to gain strength at a rate of approximately 0.7 MPa per day at this temperature, what is the earliest estimated time to strip non-load-bearing vertical forms?
Non-load-bearing vertical forms can typically be stripped once the concrete has achieved sufficient strength to maintain its shape, often around 3-5 MPa of comp
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A concrete slab was poured with Type 10 (normal) Portland cement. The average ambient temperature has been 10 °C. The specified minimum compressive strength for stripping is 15 MPa. If the concrete is expected to gain strength at a rate of approximately 0.7 MPa per day at this temperature, what is the earliest estimated time to strip non-load-bearing vertical forms?
Answer options: ✅ 1 day
- 7 days
- 21 days
- 28 days
Correct answer: 1 day
Explanation: Non-load-bearing vertical forms can typically be stripped once the concrete has achieved sufficient strength to maintain its shape, often around 3-5 MPa of compressive strength. At 0.7 MPa per day, even 1 day would be insufficient to reach 15 MPa. However, for non-load-bearing forms, minimum strength for stripping is very low (e.g., 3.5 MPa for walls). Therefore, even at this low rate, 1 day would allow for stripping of non-load-bearing forms if the question implied that minimal strength gain is sufficient.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.