According to the National Building Code of Canada (NBC) 2020 and good construction practice, when can horizontal soffit forms and shores be removed from a suspended concrete slab that is designed to carry full service loads?
The removal of horizontal soffit forms and shores is a critical structural decision. It should only occur after the concrete has gained sufficient strength, typ
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: According to the National Building Code of Canada (NBC) 2020 and good construction practice, when can horizontal soffit forms and shores be removed from a suspended concrete slab that is designed to carry full service loads?
Answer options:
- After 3 days, regardless of temperature.
- Once the concrete has achieved 50% of its specified compressive strength. ✅ Only after the concrete has achieved its specified compressive strength and passes a structural engineer's inspection, typically requiring 70-85% of f'c for partially de-shored systems or 100% for full de-shoring.
- When the concrete appears dry to the touch.
Correct answer: Only after the concrete has achieved its specified compressive strength and passes a structural engineer's inspection, typically requiring 70-85% of f'c for partially de-shored systems or 100% for full de-shoring.
Explanation: The removal of horizontal soffit forms and shores is a critical structural decision. It should only occur after the concrete has gained sufficient strength, typically a significant percentage (e.g., 70-85% for re-shoring, or 100% for full removal) of its specified design strength (f'c), and is always subject to a structural engineer's approval based on site-specific testing and evaluation to ensure safety and prevent structural damage.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.