A carpenter is framing a new window opening that is 1.5 metres wide in a load-bearing wall. The wall supports one residential floor and a roof. What is the minimum depth of a double header made of No. 2 SPF lumber required for this opening?
For a 1.5 metre clear span supporting one floor and a roof, a double 38x235 mm (2x10) No. 2 SPF header is usually the minimum required according to prescriptive
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpenter is framing a new window opening that is 1.5 metres wide in a load-bearing wall. The wall supports one residential floor and a roof. What is the minimum depth of a double header made of No. 2 SPF lumber required for this opening?
Answer options: ✅ 38 mm x 235 mm (2x10)
- 38 mm x 184 mm (2x8)
- 38 mm x 286 mm (2x12)
- 38 mm x 140 mm (2x6)
Correct answer: 38 mm x 235 mm (2x10)
Explanation: For a 1.5 metre clear span supporting one floor and a roof, a double 38x235 mm (2x10) No. 2 SPF header is usually the minimum required according to prescriptive tables in the National Building Code of Canada.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.