A residential wall assembly in Ontario consists of 38x140 mm (2x6) wood studs at 400 mm O.C., 12.7 mm gypsum board, 12.7 mm exterior oriented strand board (OSB), and 12.5 mm fibre-cement siding. If the stud cavities are fully filled with fiberglass batt insulation (RSI 2.85 m²·K/W per 100 mm), what is the approximate effective RSI of the clear-wall section assuming 15% framing factor for the studs?
Calculate the RSI for 140 mm fiberglass: (2.85/100) * 140 = 3.99 m²·K/W. This question asks for the clear-wall section, meaning the section away from thermal br
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A residential wall assembly in Ontario consists of 38x140 mm (2x6) wood studs at 400 mm O.C., 12.7 mm gypsum board, 12.7 mm exterior oriented strand board (OSB), and 12.5 mm fibre-cement siding. If the stud cavities are fully filled with fiberglass batt insulation (RSI 2.85 m²·K/W per 100 mm), what is the approximate effective RSI of the clear-wall section assuming 15% framing factor for the studs?
Answer options: ✅ RSI 3.9 m²·K/W
- RSI 3.5 m²·K/W
- RSI 3.1 m²·K/W
- RSI 2.7 m²·K/W
Correct answer: RSI 3.9 m²·K/W
Explanation: Calculate the RSI for 140 mm fiberglass: (2.85/100) * 140 = 3.99 m²·K/W. This question asks for the clear-wall section, meaning the section away from thermal bridges like studs. The RSI of the insulation itself is the dominant factor in the clear wall when fully filled. Add surface and sheathing resistances, but the insulation is key.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.