What is the purpose of a 'keyway' or 'keying' when pouring a new concrete wall on an existing footing?

A keyway is a groove formed in the footing (or first pour) that interlocks with the subsequent concrete pour, creating a mechanical bond that resists lateral sh

Start free practice for Carpenter Red Seal Exam Prep

300 questions · no signup required · 40 free questions per day

Start Practice →

Question: What is the purpose of a 'keyway' or 'keying' when pouring a new concrete wall on an existing footing?

Answer options: ✅ To create a mechanical bond between the old and new concrete, preventing lateral movement.

  • To provide a path for rebar to connect the two pours.
  • To allow for expansion and contraction of the concrete.
  • To drain excess water from the wall footing.

Correct answer: To create a mechanical bond between the old and new concrete, preventing lateral movement.

Explanation: A keyway is a groove formed in the footing (or first pour) that interlocks with the subsequent concrete pour, creating a mechanical bond that resists lateral shear forces.

Start free practice for Carpenter Red Seal Exam Prep

300 questions · no signup required · 40 free questions per day

Start Practice →

More about Carpenter Red Seal Exam Prep

Related Questions

More for Carpenter Red Seal Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Carpenter Red Seal Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.