Electrician Red Seal · Question
A journeyperson is performing an insulation resistance test on a brand new 15 kV medium-voltage cable connecting a transformer to a switchgear. The cable is approximately 100 metres (328 feet) long. After applying the test voltage for 10 minutes and recording the value, they note the insulation resistance reading is unusually low, even after considering temperature correction. What additional test is most critical to perform before energizing the cable?
Given an unusually low insulation resistance reading on a new medium-voltage cable, a High Potential (Hipot) test is critical. A hipot test applies a DC or AC v
Start free practice for Electrician Red Seal
150 questions · no signup required · 40 free questions per day
Question: A journeyperson is performing an insulation resistance test on a brand new 15 kV medium-voltage cable connecting a transformer to a switchgear. The cable is approximately 100 metres (328 feet) long. After applying the test voltage for 10 minutes and recording the value, they note the insulation resistance reading is unusually low, even after considering temperature correction. What additional test is most critical to perform before energizing the cable?
Answer options:
- A power factor (dissipation factor) test
- A loop impedance test
- A voltage drop test under load ✅ A high potential (hipot) test
Correct answer: A high potential (hipot) test
Explanation: Given an unusually low insulation resistance reading on a new medium-voltage cable, a High Potential (Hipot) test is critical. A hipot test applies a DC or AC voltage significantly higher than the operating voltage for a specific duration to stress the insulation, revealing potential defects or weaknesses that might lead to failure in service. While a power factor test could reveal general insulation degradation, a hipot test is a more direct way to find specific defects that could be causing the low megger reading, allowing for repair or replacement before an in-service failure.
Start free practice for Electrician Red Seal
150 questions · no signup required · 40 free questions per day
More about Electrician Red Seal
Related Questions
- A residential garage is to be wired with a 15 A, 120 V duplex receptacle. According to the Canadian Electrical
- During a renovation of a commercial kitchen, an electrician needs to replace an old single-phase, 240 V, 5 kW
- A commercial kitchen is being renovated, and several new 4 kW, 208 V, single-phase electric ovens are being in
- What is the minimum working space depth required in front of an electrical panel rated 200 A, 120/240 V, locat
- A Red Seal electrician is setting up temporary power for a construction site. The main temporary service is a
- A new industrial facility requires a 600 V, three-phase, 150 A feeder to supply a motor control centre. The co
More for Electrician Red Seal candidates
Practice tests
Question explanations
- A residential garage is to be wired with a 15 A, 120 V duplex receptacle. According to the Canadian Electrical
- During a renovation of a commercial kitchen, an electrician needs to replace an old single-phase, 240 V, 5 kW
- A commercial kitchen is being renovated, and several new 4 kW, 208 V, single-phase electric ovens are being in
- What is the minimum working space depth required in front of an electrical panel rated 200 A, 120/240 V, locat
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Electrician Red Seal Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.