An electrician is commissioning a new 7.5 kW (10 hp), 460 V, three-phase induction motor with a service factor of 1.15. What is the maximum continuous mechanical output power this motor can deliver without exceeding its insulation temperature rise rating?
The service factor (SF) indicates how much overload a motor can handle continuously without damage. The maximum continuous output is the nominal power multiplie
Start free practice for Electrician Red Seal
150 questions · no signup required · 40 free questions per day
Question: An electrician is commissioning a new 7.5 kW (10 hp), 460 V, three-phase induction motor with a service factor of 1.15. What is the maximum continuous mechanical output power this motor can deliver without exceeding its insulation temperature rise rating?
Answer options:
- 7.5 kW (10 hp) ✅ 8.625 kW (11.5 hp)
- 6.52 kW (8.7 hp)
- 9.375 kW (12.5 hp)
Correct answer: 8.625 kW (11.5 hp)
Explanation: The service factor (SF) indicates how much overload a motor can handle continuously without damage. The maximum continuous output is the nominal power multiplied by the service factor: 7.5 kW * 1.15 = 8.625 kW (10 hp * 1.15 = 11.5 hp).
Start free practice for Electrician Red Seal
150 questions · no signup required · 40 free questions per day
More about Electrician Red Seal
Related Questions
- A residential garage is to be wired with a 15 A, 120 V duplex receptacle. According to the Canadian Electrical
- During a renovation of a commercial kitchen, an electrician needs to replace an old single-phase, 240 V, 5 kW
- A commercial kitchen is being renovated, and several new 4 kW, 208 V, single-phase electric ovens are being in
- What is the minimum working space depth required in front of an electrical panel rated 200 A, 120/240 V, locat
- A Red Seal electrician is setting up temporary power for a construction site. The main temporary service is a
- A new industrial facility requires a 600 V, three-phase, 150 A feeder to supply a motor control centre. The co
More for Electrician Red Seal candidates
Practice tests
Question explanations
- A residential garage is to be wired with a 15 A, 120 V duplex receptacle. According to the Canadian Electrical
- During a renovation of a commercial kitchen, an electrician needs to replace an old single-phase, 240 V, 5 kW
- A commercial kitchen is being renovated, and several new 4 kW, 208 V, single-phase electric ovens are being in
- What is the minimum working space depth required in front of an electrical panel rated 200 A, 120/240 V, locat
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Electrician Red Seal Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.