A 100 kVA, 600V to 120/208V, three-phase, delta-wye transformer is installed. What is the full load current on the secondary side?

For a three-phase system, the formula for current is I = VA / (V * √3). On the secondary side: I = 100,000 VA / (208 V * 1.732) ≈ 277.8 A. Using the √3 is cruci

Start free practice for Electrician Red Seal

150 questions · no signup required · 40 free questions per day

Start Practice →

Question: A 100 kVA, 600V to 120/208V, three-phase, delta-wye transformer is installed. What is the full load current on the secondary side?

Answer options: ✅ 277.8 A

  • 96.2 A
  • 481.1 A
  • 166.7 A

Correct answer: 277.8 A

Explanation: For a three-phase system, the formula for current is I = VA / (V * √3). On the secondary side: I = 100,000 VA / (208 V * 1.732) ≈ 277.8 A. Using the √3 is crucial for three-phase calculations.

Start free practice for Electrician Red Seal

150 questions · no signup required · 40 free questions per day

Start Practice →

More about Electrician Red Seal

Related Questions

More for Electrician Red Seal candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Electrician Red Seal Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.